Srinagar, Dec 07 (KS) :  The Divisional Commissioner Kashmir today reviewed  progress on Comprehensive Sewerage Scheme in Zone-III of  Greater Srinagar under  Languishing  Scheme of erstwhile JnNURM executed by H&UDD/UEED.

The meeting was attended by  Chief Engineers of PHE, PWD Central, General Manager NBCC, officers of SMC and representatives of the area.

The meeting was informed that Trunk Sewer Line has been 99 percentcompleted while Lateral Sewer Line has been entirely  completed besides 60 MLD STP is near completion with 98% work done.

It was further informed that due to  non-availability of fronts for Trunk Sewer Line at 90 feet road for shifting of 16   Shops & Re-Alignment of PHE pipes at Alamgiri Bazar the remaining work is pending for completion.

On the occasion, Divisional Commissioner directed concerned officers to speed up the execution of work so the concerned area doesn’t face inconvenience due water logging. 

He enjoined concerned to make the arrangements for providing the electricity to ensure the operation of the STP.

He also instructed for completion of  rehabilitation process of shopkeepers  so the remaining segment of Sewer Line is completed.(KS)